Fill an application form and attach the following
Wiring certificate from a certified wireman.
One passport photo
Copy of your national ID (both sides).
A letter from your village chairman proving ownership of the land.
Copy of the wayleave form if poles and wires are to pass through people’s land.
Copy of trade licence for sole proprietorships.
Company seal and certificate of incorporation (for companies).
Pay inspection charges when submitting the application form.
- Single phase Ugx. 38,000/=
- Three phase Ugx. 80,000/=
Upon payment of the inspection charges, a surveyor visits the site for inspection
Upon successful inspection, a client pays the connection fee
No pole service – 470,000/=
One pole service – 2,800,000/=
Connection is done after receipt of connection fee